Eagle Mountain WWTP Headworks
Eagle Mountain · Utah County
- Contract Value
- $4.0M
- Grit Removal & Influent Screens
- New Headworks
- Location
- Eagle Mountain
- County
- Utah County
- Year
- 2024
- Status
- Complete
- Client / Owner
- Eagle Mountain City / Aqua Engineering
Project Overview
VanCon built a new headworks building and flow meter vault in an existing facility and installed influent screens, grit washing and removal equipment, a grit pump, slide gates, and connections to existing piping to divert influent lift station through the headworks building before supplying the ox ditch. VanCon's fabrication shop made the interior and exterior steel staircases and handrail and the channel supports and plates for the electrical room.
Project Highlights
- New headworks building and flow meter vault
- Influent screen installation
- Grit washing and removal equipment
- Grit pump and slide gates
- Connections to existing piping for influent diversion
- Interior and exterior steel staircases fabricated in-house
- Handrail and channel supports fabricated in-house
- Electrical room channel supports and plates
Related Projects
Ashley Valley WTP Chain & Flight Replacement
CompleteAshley Valley · Uintah County · 2018
VanCon demolished the deteriorated chain & flight mechanisms in both the North and South Basins and installed new devices which included shafts, chains & flights, motors & drives, return rails, installation and start-up of electrical and instrumentation. Existing handrails were modified and permanent ladders were added. Instrumentation, controls and weather shields were installed. CM/GC additions included an extra stainless-steel platform with a retractable ladder to improve basin access, and a baffle to protect the polymer sludge rakes from being destroyed by influent water.
Contract Value
$0.6M
North & South Chain Replacement
2 Basins
View Project →
Salem WRF
CompleteSalem · Utah County · 2022
VanCon built a new wastewater reclamation facility with an operations building, a maintenance building, an electrical building, an influent pump station with mechanical and bypass bar racks, a headworks building with washer/compactor, grit classifier, and grit chambers, an anaerobic pre-selector with RAS pumps, a three-ring Orbal ditch, clarifiers, a process building with UV open channel disinfection, screw press, and alum feed systems, WAS pumps, a solids storage tank, odor control, and combustible gas monitoring. The water table onsite was 3 feet deep — vaults 15 to 20 feet deep required continual dewatering throughout the project.
Contract Value
$16.3M
Full WRF New Construction
3-Ring Orbal
View Project →
Springdale WTP
CompleteSpringdale · Washington County · 2018
VanCon removed the existing chemical room, chlorine room, and clearwell, and constructed a new water treatment plant with meter and control valve vault, office building, CMU block wall, and generator reinstallation.
Contract Value
$4.5M
Water Treatment Plant
Full Replacement
View Project →
Ready to Start Your Project?
Let’s talk about what VanCon can deliver for your community.
Request a Bid